National Cranberry Cooperative(NCC) 사례분석

National Cranberry Cooperative(NCC) 사례분석
National Cranberry Cooperative(NCC) 사례분석.pptx


목차

Process Analysis of RP1
Productivity and Financial Bottlenecks
Short-Term Analysis
Long-Term Analysis
Conclusion


본문

Productivity Bottleneck 1: Drying Process2: Quality Grading & Drying for Bulks3: Inefficient Positioning of Process
Financial BottleneckWorkforce


Bottleneck at Drying procedure
Overtime Costs & Truck Queue

To solve the problem,
Minimizing the Cost
Remove Truck Queue


Amount of berries
: 75 X 243 = 18225
But, we assumed it is 19000 for easiness of the calculation

Total work time except overtime
: 12 1 (for lunch) = 11hrs.


Total amount of wet berries per hour
: (19000 X 0.7) / 11 = 1210




키워드
사례분석, CooperativeNCC, Cranberry, National, Cooperative